Item Coversheet

MEETING DATE: 11/15/2022
AGENDA ITEM NO.: I.2.

Approval of Final Payment for Construction Contracts -Consent Agenda

Board of Trustees
Executive Summary of Board Agenda Item


TITLE:
Approval of Final Acceptance of Work and Partial Payment for Andress High School Additions and Renovations - Performing Arts Center, CSP No. 18-079, Project No. 17.626, to Urban Associates, Inc. (2016 Bond Funds - $748,354.75)
JUSTIFICATION STATEMENT:
(Approval is needed to proceed with final acceptance and partial payment for the project as per Board Policy)
PURPOSE OF AGENDA ITEM:Action
TO BE HELD IN:Open Session
TEXAS GOVERNMENT CODES:
AUTHORITY FOR ACTION:Legal/Local Policy
STAFF RESPONSIBLE:Alan Wiernicki/Irene Ramirez
DISTRICT IMPROVEMENT PLAN OBJECTIVE, GOAL OR NEED ADDRESSED:
SUMMARY:

The Board of Managers at its meeting November 17, 2014, approved revisions to Board Policy CV (Local): Facilities & Construction, as follows: “The District shall not make final payments for construction or the supervision of construction until the work has been completed and the Board has accepted the work.” The District maintains retainage in an amount of at least five percent (5%) of the contract value until final payment is made. Administration is providing the Board documentation to the effect that the conditions for Final Acceptance and Final Payment set out in the contract have been satisfied.

 

The original project construction contract budget was established at $26,500,946.00, with the actual final construction cost of $26,186,835.48.  On March 9, 2021, the Board approved the release of partial retainage for the completion and final acceptance of the Field House for $202,218.68, representing 0.77%, of the final construction cost.

 

The conditions of Final Acceptance of the work for the Performing Arts Center was achieved on September 27, 2022. The partial retainage of $748,354.75, equates to 2.86% of the final construction cost. This is a result of the assessment of 102 calendar days of liquidated damages against the remaining balance on the construction contract. Furthermore, the withholding of $261,868.35, representing 1.00% of the final construction cost is being withheld for the pending installation of audio/visual equipment.

ADMINISTRATIVE RECOMMENDATION/MOTION:

It is recommended that the Board approve the final acceptance of the work and partial payment for Andress High School Additions and Renovations - Performing Arts Center, CSP No. 18-079, Project No. 17.626, to Urban Associates, Inc., in the amount of $748,354.75.

FUNDING SOURCE:689X Bond Funds ACCOUNT NO.: 689.81.6624.001.99.603.626 
FISCAL IMPACT AND COST:
  • IMMEDIATE: $748,354.75
  • FUTURE/ONGOING:
IMPACT ON OTHER FUNCTIONS/OPERATIONS: 
CONSEQUENCES OF NON-APPROVAL:
IMPLEMENTATION TIMELINE:
COMMENTS RECEIVED, IF ANY:
ATTACHMENTS:
Description
Final Payment Package